1. Is My Building Covered by Local Law 87?
A building is covered when it is over 50,000 gross square feet. A tax lot is covered when its buildings together exceed 100,000 gross square feet. Condominium buildings that together exceed 100,000 are covered too.
The CBL, or Covered Buildings List, is DOB's yearly list of buildings covered by NYC's building energy laws. The 2026 list marks each LL87 building with "On LL87 = Y".
| Lookup answer | What it means | Next step |
|---|---|---|
| On the 2026 LL87 list | DOB lists this BBL for LL87 | Plan the audit for the due year below |
| Not on the 2026 list | DOB doesn't list this BBL for LL87 | Check the floor area against the thresholds above |
| Can't match yet | We can't tie the address to a BBL | Search by the 10-digit BBL |
2. LL87 Due Dates: When Is the Report Due?
The report is due in the calendar year whose last digit matches the last digit of the building's tax block. A tax block ending in 7 files in 2027, then in 2037.
A BBL is NYC's 10-digit borough-block-lot number for a tax lot, and a BIN identifies one building on it. The tax block is digits 2 to 6 of the BBL. For BBL 1008350041, the block is 00835, so the report is due in 2035.
DOB's list does not print a due year for each building, so the lookup applies this rule to the BBL.
| Tax block ends in | Due year |
|---|---|
| 6 | 2026 |
| 7 | 2027 |
| 8 | 2028 |
| 9 | 2029 |
| 0 | 2030 |
| 1 | 2031 |
| 2 | 2032 |
| 3 | 2033 |
| 4 | 2034 |
| 5 | 2035 |
Where the Due-Year Rule Comes From
The rule is NYC Administrative Code §28-308.4.1. Its official chart starts the first cycle in 2013, and each building refiles every 10 years.
The report is due by December 31 of the due year. DOB moved that date by service notice for the 2025 and 2026 filing years, each time for that year only.
| Filing year | Moved deadline | DOB source |
|---|---|---|
| 2025 (blocks ending in 5) | March 31, 2026 | 2025 service notice |
| 2026 (blocks ending in 6) | March 31, 2027 | November 16, 2026 notice |
DOB's February 27, 2026 reminder said 2025 extensions did not apply to 2026 and set December 31, 2026. The November 16 notice has since replaced that date. See DOB Service Updates, checked 2026-11-27.
City-owned buildings follow a separate staggered schedule, not the tax block. A cooperative with covered buildings on different blocks may file one combined report, due with its last building.
3. LL87 Requirements: The Energy Audit and EER
An Energy Efficiency Report (EER) is the LL87 filing. It summarises an energy audit and the building's retro-commissioning, and a registered design professional files it with DOB.
An energy audit is a survey of how the building uses energy and which upgrades would save it. Retro-commissioning is testing an existing building's systems and tuning them to run as designed.
DOB's guide to filing an EER lists the forms. Each EER also includes DOB's Deep Energy Retrofit Plan Analysis tool.
What the Audit and RCx Must Deliver
The energy audit must at least match a Level 2 audit under ASHRAE Standard 211-2018. Audit data goes into the U.S. Department of Energy's Asset Score Audit Template.
Retro-commissioning follows NEBB Standard S120-2016, and deficiencies are fixed before filing. The rule's checklist includes:
- Pre-test cleaning and functional testing of boilers, chillers, air handlers and controls
- Setpoints, sensor calibration and simultaneous heating and cooling
- Boiler combustion tests, steam traps and pipe insulation
- Lighting controls, weather-stripping and staff training
Who Can Sign the Audit and the RCx
Neither the energy auditor nor the RCx agent may be on the building's staff. The auditor must be a registered design professional with an approved credential, such as AEE's Certified Energy Manager.
The RCx agent may be a registered design professional, a certified Refrigerating System Operating Engineer or a licensed High Pressure Boiler Operating Engineer. The agent needs one of 10 listed commissioning certifications, per 1 RCNY §103-07.
Extensions and Deferrals
A good-faith extension request is due by December 31 of the due year, and a financial hardship request by October 1. The DOB LL87 FAQ says each extension adds one year, with up to two granted.
A building under 10 years old, or substantially rehabilitated within 10 years, may defer by filing form EER1 by December 31. Its base systems must meet the energy code.
4. LL87 Penalties and Filing Fees
Missing the EER costs $3,000 in the first year and $5,000 for each additional year. Fees are paid when you file.
| Item | Amount |
|---|---|
| Initial filing (EER or deferral) | $375 |
| Extension request | $155 |
| Amendment | $145 |
| Penalty, first year without an EER | $3,000 |
| Penalty, each additional year | $5,000 |
Source: DOB, Resolving LL87 Violations, checked 2026-11-27.
How to Resolve an LL87 Violation
The penalty repeats each year until the EER is submitted. DOB won't accept a late EER until outstanding penalties are paid.
- Find the violation in DOB NOW under "Violations & Notices of Deficiency."
- Pay in DOB NOW: Safety. DOB stopped taking mailed payments on December 15, 2025.
- File the late EER.
You can challenge a violation on DOB's form within 30 days of its postmark.
5. LL87 vs. LL97
LL87 is an audit and tune-up report filed once every 10 years. LL97 sets yearly emissions limits, with a penalty of $268 per tonne of excess emissions.
LL87 audit findings feed directly into LL97 planning. The audit is often where an owner first prices the upgrades that keep a building under its LL97 limit.
Check the same building's LL97 estimate with the LL97 calculator. Our NYC permit lookup shows what mechanical work it has already filed.
6. Local Law 87 by the Numbers
DOB's 2026 list marks 16,755 tax lots (BBLs) for LL87, covering 39,646 BBL and BIN pairs. Applying the tax-block rule spreads them almost evenly across 2026 to 2035.
| Estimated due year | Tax lots |
|---|---|
| 2026 | 1,685 |
| 2027 | 1,646 |
| 2028 | 1,617 |
| 2029 | 1,714 |
| 2030 | 1,773 |
| 2031 | 1,697 |
| 2032 | 1,679 |
| 2033 | 1,703 |
| 2034 | 1,621 |
| 2035 | 1,620 |
| Borough | Tax lots on the LL87 list |
|---|---|
| Manhattan | 6,702 |
| Brooklyn | 3,791 |
| Queens | 3,004 |
| Bronx | 2,916 |
| Staten Island | 342 |
Of the LL87 lots, 4,371 have enough public data for our LL97 estimate in 2030–2034. 2,389 of them would exceed their 2030 LL97 limit at their last reported energy use.
What past LL87 audits found
Based on 7,837 NYC Local Law 87 energy audit reports filed 2019–2024 (NYC Open Data au6c-jqvf), at least 5,808 (74%) recommended one or more heating, cooling, ventilation or HVAC-control measures.
Boiler-plant work was the most common HVAC recommendation, appearing in at least 3,133 of 7,837 reports (40%), followed by HVAC controls or building management systems in at least 2,510 (32%).
Heat pump measures were recommended in at least 6 of 908 reports filed in 2019 (0.7%) and at least 138 of 1,656 reports filed in 2024 (8.3%).
Counts use the latest submission per audit, measures with status "Recommended", and at most four measure packages per report in the published file, so they are lower bounds.
FAQ
What is the easiest way to find a building's LL87 due date?
Enter the address or BBL in HVACLookout's free LL87 lookup above. It checks DOB's 2026 list and applies DOB's tax-block rule in one step, with no account. DOB's own Excel list has the same coverage flag.
What is Local Law 87?
Local Law 87 of 2009 requires large NYC buildings to file an energy audit and retro-commissioning report every 10 years. It covers buildings over 50,000 gross square feet.
When is my LL87 report due?
It is due in the year whose last digit matches your tax block's last digit, normally by December 31. A block ending in 6 is due in 2026, moved to March 31, 2027. A block ending in 7 is due in 2027.
Was the 2026 LL87 deadline extended?
Yes, to March 31, 2027. DOB's November 16, 2026 service notice moved the December 31, 2026 deadline, for the 2026 filing year only.
How current is this LL87 data?
The lookup uses DOB's 2026 Covered Buildings List, which DOB published in March 2026. We synced it on October 27, 2026.
What is the penalty for not filing LL87?
$3,000 for the first year and $5,000 for each additional year without an EER, according to DOB.
How much does it cost to file an LL87 EER with DOB?
The DOB fee is $375 for the initial filing, $155 for an extension and $145 for an amendment. The audit and retro-commissioning work are priced separately by the firm you hire.
Who can file an LL87 Energy Efficiency Report?
A registered design professional files the EER. The energy audit and retro-commissioning are certified on DOB's EERC1 and EERC2 forms.
What is the difference between LL87 and LL97?
LL87 is a 10-yearly audit and retro-commissioning report. LL97 sets yearly carbon limits with penalties; the LL97 calculator estimates them for one building.
Can I see a building's permit history from the LL87 lookup?
Yes. Each result links to our NYC permit lookup, which shows the building's DOB NOW: Build permits with mechanical work highlighted.
Find NYC Buildings With Upcoming Compliance Deadlines
On DOB's 2026 list, 1,646 tax lots have a tax block ending in 7, so their report is due in 2027. Retro-commissioning deficiencies are fixed before filing, so repair work comes up ahead of each due date.
HVACLookout tracks NYC compliance and permit signals for commercial HVAC contractors. Plans start at $79 a month for one city.